Bill a project in the stages your contract sets, one invoice per accepted deliverable, with its share of the total and a clear count of what's been paid.
Updated
Milestone invoice · sample
- Milestone 2 of 3: Build (50% of $9,000.00), delivered Aug 7, accepted Aug 14, per SOW-141 × $4,500.00$4,500.00
- Change request CR-3: data export feature, approved Jul 281 × $650.00$650.00
- Subtotal
- $5,150.00
A milestone invoice bills one stage of a project once that stage is delivered and accepted. The stages come from the contract: design 30%, build 50%, launch 20%. Each milestone is a deliverable, not a date and not a measure of effort. That's the difference from progress billing, where a contractor bills for how much of the work is complete, and from a retainer, where the client pays for time whether or not anything ships. This page covers what to put on it, a sample for milestone 2 of 3 on a $9,000 project, and how the stages should add up to the contract.
Checklist
What to include on a milestone invoice
A client approves a milestone invoice by checking it against the contract. Make that check easy with these six fields.
The milestone, named as in the contract
Use the milestone's number and name exactly as the contract has them: 'Milestone 2 of 3: Build'. If the contract says 'Beta release' and the invoice says 'Development phase', the client's accounts team will ask which payment it is.
The contract it comes from
Quote the agreement or statement of work by its number or date. Clients with several projects need it to match the invoice to a budget, and you need it if a stage is ever disputed.
What was delivered and accepted
Describe the deliverable in a few words and state when the client accepted it: 'Build delivered Aug 7, accepted by email Aug 14'. Under most milestone contracts, acceptance is what makes the payment due, so it belongs on the invoice and not only in your inbox.
Its share of the total
Show the milestone's percentage or fixed amount next to the full contract value: '50% of $9,000.00'. The client sees the stage in proportion, and anyone reading the invoice later sees the whole deal it belongs to.
What's been paid so far
List the earlier milestone invoices by number with what was paid, plus what remains after this one. 'Paid to date: $2,700.00 (invoice #2031). Remaining after this invoice: $1,800.00.' This running count keeps the last stage from being a surprise.
Extra work on its own lines
Work the client asked for outside the milestones, such as a change request, goes on a separate line with its own reference. Folding it into the milestone amount makes the stage look pricier than the contract says, and it gets queried.
Taken together, the stage invoices should equal the contract value plus approved changes, with nothing missing.
Example
Milestone invoice example
Milestone 2 of 3 on a $9,000 customer portal project, split 30% design, 50% build, 20% launch. Milestone 1 was paid on invoice #2031. The sample assumes the services aren't subject to sales tax: tax rules vary by state and country, so check yours.
Milestone invoice
- Milestone 2 of 3: Build (50% of $9,000.00), delivered Aug 7, accepted Aug 14, per SOW-141 × $4,500.00$4,500.00
- Change request CR-3: data export feature, approved Jul 281 × $650.00$650.00
- Subtotal
- $5,150.00
Invoice notes: Invoice #2044, due Sep 13 (net 30). Contract value $9,000.00. Paid to date: $2,700.00 (invoice #2031, Milestone 1: Design). After this invoice, $1,800.00 remains for Milestone 3: Launch. Change requests are billed outside the contract value.
Good to know
Milestone invoice rules worth knowing
Milestone billing is not progress billing
The two get mixed up. Progress billing charges for the share of the work that's done, measured as a percentage and typical in construction. Milestone billing charges a fixed amount when a defined deliverable is accepted. If your contract measures completion rather than deliverables, a progress invoice is the closer fit.
Acceptance terms decide when you can bill
Many milestone contracts give the client a set number of days to accept or reject a deliverable, and treat silence as acceptance after that. If yours does, the invoice can quote it: 'Deemed accepted Aug 14 under clause 6'. If the contract says nothing, get acceptance in writing before you invoice.
Tax on each stage
In many VAT countries, each milestone invoice is taxed on its own date, so it carries VAT on that stage's amount. In the US, whether a service or a digital deliverable is taxable depends on the state. Invoicor applies one tax rate per invoice, so a stage that mixes taxed and untaxed work may need two invoices; ask your accountant.
General information, not tax or legal advice. Check the specifics with an accountant or lawyer where you work.
Avoid these
Three milestone invoice mistakes
Invoicing before acceptance
Sending the invoice the day you deliver, before the client has signed off, invites them to reject both. Wait for acceptance, or the date the contract deems it accepted, and quote that date.
Stages that don't add up
Rounding a third of $10,000 to $3,333 three times leaves $1 unbilled, and a renegotiated split can leave more. Make the last milestone the remainder of the contract value, so the stages always total the contract exactly.
No running total
Each invoice on its own looks fine, but without 'paid to date' and 'remaining' the client loses track, and so do you.
Format
Send it as a PDF
Why PDF
A PDF keeps the milestone name, the acceptance date and the running totals fixed, which is what a client's project manager forwards to finance for approval.
Free, in your browser
Open this milestone template in the free generator: the example lines are already filled in. Change them, add your logo and download the PDF. No signup.
Open the generatorFrom your iPhone
The Invoicor app makes the same PDF and sends it by email or message, with your clients and usual items saved. 3 invoices free.
Get the app
Why not Word or Excel? Anyone who opens them can change the amounts, and a formula can quietly break a total. Invoicor makes PDFs only.
Pro tip
A tip for milestone invoices
Milestone pro tip
FAQ
Milestone invoicing FAQ
How do I split a project into milestones?
Can the first milestone be paid upfront?
What if the client rejects a milestone?
Where do change requests go?
How is the last milestone invoice different?
Make your milestone invoice in seconds.
Saved clients and line items, automatic totals and tax, and a clean PDF you send from your phone before you leave the job.
3 invoices free · no watermark · no subscription needed